7:45pm Call meeting to order and review agenda
7:50pm Other Commission Business:
Budget contribution from Fees acct – asked for increase
Arlington Reservoir-
Volunteer projects: Hills Pond, Reservoir, organize Land Steward meeting, land grants
Waterbodies fund – Warrant submitted, Fin Com mtg 2/27 report
Stone Road conservation area – illegal dumping referred to Legal Dept.
Walking Book subcommittee – report
Minutes: 2/16 minutes
Administrative:
8pm Notice of Intent – 0 Mystic St (behind 24 Summer St), Arlington Catholic athletic field renovation, continued from 2/16
Other Commission Business, cont’d:
Enforcement –
Item(s) not reasonably anticipated by the Chair 48 hours in advance of this meeting
Project Updates:
16 Spy Pond Pkwy (formerly 0 Spy Pond Pkwy) (91-181) –landscaping installed 6/11
Alewife Greenway (91-200) - started June, 2010, boardwalk thru cattail marsh completed 1/12
Mystic Dam (91-201) – complete, COC issued 2/17/12
Spy Pond phragmites treatment (91-208) – done on 10/5/11
Highland Fire Station (91-210) - started 8/10
30-50 Mill St (91-213) – started 8/11
Spy Pond Condos shoreline stabilztn (91-214) – started 9/10, mostly complete 11/10
Mystic Valley Parkway bridge reconstruction over Alewife (91-215) – to start 2/12, will take 1.5 yrs
59 Beverly Rd (91-217) – to start 8/10, mostly complete 5/11
Wellington Tennis Courts (91-231) – started 6/11, mostly complete 12/11
Spy Pond Rain Garden (91-236)– mostly completed 10/11
63 Beverly Road (91-233) – started 8/11, additional tree must come out, will submit new landscaping plan
Thorndike Dog Park (91-238) – started 12/11
Old Colony Lane drain repair (A11.3) – started 12/7/11