Arlington Conservation Commission
Agenda
February 17, 2011
7:45pm Call meeting to order and review agenda
7:50pm Other Commission Business:
Walking Book –search for printer/publisher
Arlington Reservoir – aquatic weed treatment needed, funding, Warrant Article
Volunteer projects: Dallin vernal pool, Hills Pond, Reservoir, organize Meadowbrook cleanup, organize Land Steward meeting
Ecofest – scheduled for 3/26/11
9 Princeton Rd – shoreline erosion, draft letter
Warrants: wetland maps, waterbodies funds
Minutes: approve 2/3 minutes
Administrative:
8pm Certificate of Compliance – 50 Lowell St, Mill Brook culvert replacement
Enforcements: sign off on DEP forms
8:30pm Viking Court- notice sent 2/8/11
8:45pm Menotomy Village Shopping Center- notice sent 2/8/11, snow removal to take place on 2/11
9pm Arlington Coal and Lumber- notice sent 2/8/11
Other Commission Business, cont’d:
Project Updates:
16 Spy Pond Pkwy (formerly 0 Spy Pond Pkwy) (91-181) – began 9/08, house up 12/09
Spy Pond aquatic weeds (91-194) - Sonar treatment on June 1, 2010, booster July 7, 2010
Alewife Greenway (91-200) - started June, 2010, fence along Alewife Brook removed
Mystic Dam (91-201) – started 10/09 Medford, herring using fish ladder, Arlington started 9/7/10
837-821 Mass Ave, CVS (91-202) – demo 11/09, remediation 2/10, drainage 3/10, swale 4/10, store open 11/10
Thorndike parking lot (91-203) - started 7/10, mostly complete by 9/8/10
Spy Pond phragmites, growing in waterbody (91-208) – 1st trtmnt 10/09, rprt rcvd 8/10, 2nd treatment 10/10
50 Lowell St (91-209) –work completed by 12/16/10
Highland Fire Station (91-210) - started 8/10
Spy Pond Condos shoreline stabilization (91-214) – started 9/10, mostly complete 11/10
6 Lawrence Ln (91-216) – started 8/10
59 Beverly Rd (91-217) – to start 8/10
Spy Pond phragmites, growing on land, various properties (91-218 thru 91-226) – site walk 9/15, photos
Winchester Flood Control projects – FEIR received, comments filed 3/26/10
Citizens Open Forum
|